Key points of operation of steel cage welder
1. Equipment debugging and parameter setting: mainly according to the steel cage needs to be made on site according to the diameter of the design drawings, the number of main bars, the distance between the main bars, the distance between the stirrup to install and set, adjust the bolt number and distance of the fixed plate and moving plate of the steel cage molding machine, set the moving plate speed.
2. Feeding operation: according to the number of main reinforcement in the design drawing, place the main reinforcement one by one on the main reinforcement feeding bracket, and place the stirrup on the feeding plate of the stirrup.
3. The main reinforcement through the reinforcement, positioning, clamping: the main reinforcement through the dividing plate and then through the fixed plate to the moving plate, according to the design requirements according to the spacing on the moving plate is fixed.
4. Welding operation: Start the switch of the steel cage hobbing welder, rotate the material plate, fixed plate and moving plate synchronically according to the preset speed, and the moving plate moves slowly forward according to the preset speed at the same time. After the stirrup is straightened by the straightening mechanism, the winding operation is carried out on the main reinforcement. At the same time, the welding operator will weld the joint of the stirrup and the main reinforcement firmly in accordance with the design requirements, and the stirrup will be cut off after welding.
5 steel cage separation and unloading: after the steel cage is completed, the moving plate continues to move forward, so that the steel cage is removed from the fixed plate, and then the steel cage and the moving plate are removed to the support frame, and then the support frame falls and the steel cage is removed from the support frame and moved to the storage area of the finished steel cage for storage.
6. Equipment return: raise the support frame to the normal height and return the moving plate to the position until the next steel cage is made.